Concrete Mixing Station Accurate Switch Order

It is necessary condition to ensure the service life of the mixing station for reasonable safety switch order. So, how can operate the switch of mixing station accurately? The following is summed up the concrete mixing station switch process:

concrete mixing station

Concrete mixing station boot sequence:

Before starting the concrete mixing station, check the water valve switch, water pump, air compressor, and open storage bin, open discharging belt – the mixing mainframe – drive belt, open ingredients (including aggregate, cement) – open water supply switch.

Concrete mixing station equipment shutdown sequence:

Ingredients (including aggregate, cement), water supply, feeding off (belt material), mixing main organs (concrete mixer tank material), discharging belt (belt material), and storage bin door off. Shut off air compressor, clean mixing tank, the water valve. Finally, switch off the power.

Zhengzhou CamelWay Machinery manufacture is one of the large-scale enterprise specializing in construction machinery. If you want to know more information about the concrete mixing station or buy it, you can contact us.

Get Support Or Price