How to debug the Concrete Mixing Station

Previous article we introduces the preparing work before debugging, then we will talk about other debugging steps:

Unit commissioning

Unit testing is necessary according to the following order: the discharge belt conveyor to mixing console, the feeding belt conveyor – grain belt scale – powder spiral scales to speed screw conveyor, pneumatic system and water supply system.    concrete mixing station

no-load test

In the following order boot on the no-load test: air compressor to belt conveyor mixture, stirring the host – the original aggregate belt conveyor – aggregate belt scale – powder spiral scales – speed adjustment screw machine to cement screw conveyor, water supply system.

load test

No-load test run after everything is right, and then to load test, and active after manual first, unit load test first, after the load test.