Installation and Adjustment of Concrete Batching Plant

The installation and adjustment of concrete batching plant is very important for production. So Zhengzhou CamelWay Machinery would like to introduce the method to you.

concrete mixing station

  1. After receipt, check if the spare parts and the technical files are complete according to the packing list and if there is some damage in the machine or parts .

2 .Users should lay the foundation well on the basis of instruction diagram.

  1. Install and set the machine as the diagram indicates, and keep each component horizontal
  2. When the whole machine is in position, install the sensor and disassemble fixed bolts of weighing hopper, keeping the weighing hopper in normal working state.

5 . Check if each conveying part is flexible and whether the junction bolts are loose.

  1.  The electric circuit includes main power wire and each motor cable, sensor cable and remote controller cable. And you should install it according to instruction

7 . Run the No-load test and check if the moving direction of each motor is right.

  1.  Run the imitation test of batching circulation as required. Set the weighing date of different materials and check if it can batching recurrently and automatically.

As a professional concrete batching plant producer, Zhengzhou CamelWay Machinery has produced concrete batching equipment which can satisfy your different requirements. If you are interested in the concrete mixing equipment, please feel free to contact us.