Preparation work before debugging the host machine of concrete mixing plants

1. Check the every component of the host machine of concrete mixing plant whether the lubricant oil is in good condition and sufficient. When debugging, check the four shaft end sealing plates in the mixing drum whether there is oil leakage.

2. Check the installation condition of every component of the host machine in the concrete mixing plant, and check whether the connection bolts are tight and connection of chain is reliable.
concrete batching plant

3. Check whether the configured pneumatic system is normal and the discharging door is in the closing place.

4. Check whether there are materials in the mixing drum of the host machine of concrete mixing plant, and fasten the lining plate, mixing blades and bolts of mixing arm again to prevent them from dropping out.

5. Check the matched electric system whether it is normal.

6. Check whether the matched supply systems of water, aggregate and powder are normal.

7. The gap between the mixing blades and lining plate of the host machine of concrete mixing plant should not exceed 5mm.